Client: BMA Saraji Mine

Location: Dysart, Queensland

Value: $1.18M

Duration: 5 weeks

Status: Completed (2024)

By reserves, Saraji Mine in Queensland’s Bowen Basin is the fourth largest coal mine in Australia. During a major shutdown, Wisely carried out major structural upgrades to the mine’s train load out facility, including:

  • Upgraded wear plates and the external bin structure
  • Removal of the clam shell doors for overhaul
  • Bin head structure replacement
  • Bin gantry connection replacement.

Completed within a five-week shutdown program, the works were delivered safely and efficiently, extending the reliability of critical infrastructure and supporting ongoing production at Saraji Mine.