Major Overhaul – Loops 3 & 4 Half Life Loop Outage, Goonyella Riverside Mine

Mining

Client: BMA Goonyella Riverside Mine

Location: Moranbah, Queensland

Value: $500K

Duration: 3 weeks

Status: Completed (2025)

Wisely was engaged to deliver a major overhaul of Loops 3 and 4 at Goonyella Riverside Mine, one of the Bowen Basin’s largest coking coal operations. The project involved significant upgrades to screening equipment and associated infrastructure, including: 

  • Replacement and upgrades to two deslime screens, two float screens and one sink screen 
  • Replacement of centrifuge and associated chutes, underpipes and pipework
  • Structural remedial works.

Delivered over a three-week program, the upgrades extended the service life of critical processing equipment and improved the reliability of coal handling operations at Goonyella Riverside Mine.